Here is a list of facilities related activities.
Dallas Campus Modernization
* The 8th and 11th floor updates are fully completed. We will be installing branding and Dear World photos throughout the Addison campus and will be done over the coming months. The 9th floor changes are underway to make this a large meeting area, breakroom space, and conference center. This work will be completed by early November..
Vermont Campus Activities
Emergency Repairs to Underground Pipes
* Work is underway in the front of the main building to our aged pipes between our underground oil tanks and the building. This work will impact traffic and handicap parking and will be completed in early November.
Parking Management System Upgrades
* We will be rolling out new parking management software in the coming months. This new system will help with parking enforcement, notification to drivers of issues with vehicles, and an automated ticketing process.
Electrical Upgrade Project
* The electrical infrastructure project includes replacing the aging electrical components in the main building over the next few years. This work is well underway with the exterior work finished for the most part and interior work well underway for the foreseeable future. Please be mindful of cordoned off areas.
Dewey Painting
* The Dewey building painting is completed.
Parking Garage Maintenance
* The parking garage work is near completion. The contractor will be back mid-October to complete several other projects. We will cordon off areas as needed throughout the project.
Storm Water Repairs
* We have two emergency projects on the back access road that require immediate repair. This work will be completed in late October. We don’t expect major impacts to parking or traffic flow.
Logging on NLGroup Property
* As part of our woodland conservation plan, we will be logging two large portions of our wooded areas this winter. This will impact the par course, however alternative routes will be available.
Life Safety
* We will be conducting shelter in place (lockdown) drills before the end of this year on BOTH campuses. We will have information coming out ahead of time to educate occupants on procedures and expectations. We will partner with local authorities to participate and answer questions following the exercise.